Statement

Careful works raise the gable wall above the roof by a cornice that bounds the triangle in front, the Windberge or Wimperge; a drip is worked under it so that the roofing lies beneath, rising slightly toward it. The coping stones are bonded with the wall, bed joints horizontal or square to the gable line; their thickness need only give a safe bearing. Raking cornices need no undercut, since water runs off over the corners. Their height has no fixed proportion to the gable, being relatively larger on small gables; suitable heights come from dividing the base of the gable into 6 to 9 parts (Fig. 1049: one eighth). Crockets are cut one per coping stone or set on a separate rib.

Formula

hc=B/n,n∈[6,9]

Sources

  • „im Allgemeinen können passende Verhältnisse gefunden werden aus der Teilung der Grundlinie des Giebels in 6 bis 9 Teile“
    “in general, suitable proportions can be found by dividing the base line of the gable into 6 to 9 parts”

    Ungewitter 1892, p. 450 (scan)

  • Ungewitter 1892, p. 451 (scan), Fig. 1049

  • „eine Wassernase angearbeitet, unter welche die Dachdeckung sich in der Weise legt, dass sie sich um ein Geringes nach derselben hebt“
    “a drip is worked on, under which the roofing lies in such a way that it rises slightly toward it”

    Ungewitter 1892, p. 470 (scan), Fig. 1084, 1084a

  • Ungewitter 1892, p. 471 (scan), Fig. 1084b, 1084c, 1084d, 1084e